Subprocess: Pre-Phase A: Concept Studies
Purpose: During Pre-Phase A, a pre-project team studies a broad range of mission concepts that contribute to program and Mission Directorate goals and objectives. These advanced studies, along with interactions with customers and other potential stakeholders, help the team to identify promising mission concept(s) and draft project-level requirements. The team also identifies potential technology needs (based on the best mission concepts) and assesses the gaps between such needs and current and planned technology readiness levels. These activities are focused toward a Mission Concept Review and KDP A.
Organization: ORG
Task |
Purpose |
Suggested Roles |
Task Lead(s) |
Estimated Completion Date |
Actual Completion Date |
Documents |
|||||
---|---|---|---|---|---|---|---|---|---|---|---|
Document |
Instructions and Samples |
Document Lead(s) |
Estimated Completion Date |
Actual Completion Date |
Document Location(s) |
||||||
Administration |
The purpose of this task is to provide basic administrative subtasks such as user and document management. |
Pre-Phase A Manager, |
Document Library |
||||||||
Headquarters and Program Products |
The purpose of this task is to provide Headquarters and Program-level products for the Flight Project. |
Pre-Phase A Manager,
|
Announcement of Opportunities (AOs) |
||||||||
Formulation Authorization Document (FAD) (Approved) |
|||||||||||
Program Requirements on the Project Plan (Draft) |
|||||||||||
Reviews |
|||||||||||
Approvals |
|||||||||||
Project Technical Products. |
The purpose of this task is to provide Technical products for the Flight Project. |
Pre-Phase A Manager,
|
Mission Concept Report (Preliiminary) |
||||||||
Reviews |
|||||||||||
Approvals |
|||||||||||
Project Planning, Cost, and Schedule Products |
The purpose of this task is to provide Planning, Cost, and Schedule products for the Flight Project. |
Pre-Phase A Manager,
|
Integrated Baseline (Draft) |
||||||||
Reviews |
|||||||||||
Approvals |
|||||||||||
Key Decision Point (KDP) Readiness Products |
The purpose of this task is to provide Key Decision Point (KDP) Readiness products for the Flight Project. |
Pre-Phase A Manager,
|
Standing Review Board Report (RB) (Final) |
||||||||
Project Manager Recommendation (includes response to SRB Report, as applicable) (Final) |
|||||||||||
CMC Recommendation (Final) |
|||||||||||
Program Manager Recommendation (Final) |
|||||||||||
MD-PMC Recommendations (for Category I Projects, only) (Final) |
|||||||||||
Governing PMC Recommendation (Final) |
|||||||||||
Reviews |
|||||||||||
Approvals |
|||||||||||
Review Packages |
The purpose of this task is to provide Review Packages products for the Flight Project. |
Pre-Phase A Manager,
|
Key Decision Point (KDP) A Package |
||||||||
Acquisition Strategy Planning Meeting (ASPM) Package |
|||||||||||
Mission Concept Review (MCR) Package |
|||||||||||
Reviews |
|||||||||||
Approvals |
|||||||||||
Analysis |
The purpose of this task is to generate reports from the data resulting from the subprocess. |
Pre-Phase A Manager,
|
Administration Reports |
||||||||
Headquarters and Program Reports |
|||||||||||
Project Technical Reports |
|||||||||||
Project Planning, Cost, and Schedule Reports |
|||||||||||
Key Decision Point (KDP) Readiness Reports |
|||||||||||
Review Packages Reports |
|||||||||||
Reviews |
|||||||||||
Approvals |
Mockup (html)
Implementation (html)